Franklin Farms is a 1,400-acre site in Holly Ridge, Louisiana on which Meta will be building a $10 billion, 1.5 GW data center complex.
Meta is partnering with Entergy1 to install two natural gas-fired combined cycle turbines at the site, providing a total of 1.5 GW of power.2 Meta has pledged to match this with 1.5 GW of “100% clean and renewable energy” in the form of carbon credits.1